Fictional completed example
RAMS: strip and re-tile, 12 Sample Street
Example Roofing Ltd · 12 Sample Street, Exampletown EX1 2AB
- Job
- Strip the existing concrete tiles from the front and rear pitches of a two-storey house, replace felt and battens, and re-tile. A small chimney flashing is included. No asbestos survey has been provided, so any cement sheet or suspect insulation stops the job. The pavement at the front stays open to the public.
- Dates and people
- 2026-11-03 to 2026-11-07. 3 operatives.
- Equipment
- Tile hoist, Roof ladder with ridge hook, Independent scaffold to the eaves, Debris chute
Fictional sample for demonstration. The company, the address and the people are invented. A competent person must review any real RAMS before work starts.
Site notes
- School-run footpath along the front of 12 Sample Street between 08:00 and 09:15
- Two roof lights on the rear pitch, not shown on the client's sketch
- Overhead telephone line at the gable, not a power line, still kept clear of the hoist
First-aid kit is in the van. Assembly point is the lamp post outside 12 Sample Street. The fictional client contact is A. Sample on 01632 960900.
Risk assessment
Scores use a 5 × 5 matrix. Risk is likelihood times severity.
| Hazard | Who | Initial | Residual |
|---|---|---|---|
Fall from the eaves, an opening, or through a fragile roof light
| Operatives on this job; Other trades and the client on site | 15 High | 5 Medium |
Tiles, battens or tools falling onto people below
| Other trades and the client on site; People passing 12 Sample Street | 12 High | 4 Low |
Manual handling of tiles, timber and lead
| Operatives on this job | 12 High | 4 Low |
Contact with a cable in the loft or the overhead line at the gable
| Operatives on this job | 10 High | 5 Medium |
Disturbing asbestos cement soffits or old insulation
| Operatives on this job; Other trades and the client on site | 10 High | 5 Medium |
Dust and cuts from disc cutting tiles
| Operatives on this job | 9 Medium | 4 Low |
Method statement
- Sign in with the client, confirm the scaffold handover, and walk the ground for the pavement, the line and the roof lights.Client contact confirmed, scaffold handover checked, and the pavement, overhead line and roof lights walked before anyone goes up.
- Brief every operative on this RAMS. No one goes up until the brief is signed.Brief signed by everyone going on the roof. No access until that is done.
- Set the exclusion zone on the pavement and the rear garden before the first tile comes off.Barriers and signs in place, banksman present, footpath diversion agreed.
- Cover or barrier the roof lights, then strip in small areas so the working edge stays protected.Roof lights covered or barriered before stripping. Strip in small areas so the working edge stays guarded.
- Lower waste by chute. Do not bomb tiles off the roof.Chute or hoist only. The banksman holds the drop zone. Tiles are not thrown.
- Felt, batten and tile in the agreed order, keeping the hoist clear of the gable line.Hoist kept clear of the gable line and the overhead cable. Packs landed on the scaffold, not on the open edge.
- Complete the chimney flashing from the scaffold, not from a leaning ladder.Flashing done from the scaffold. No leaning ladder against the stack.
- Clear the roof, inspect the garden and pavement, and remove access only when the roof is clear of people.Roof clear of people before access is struck. Garden and pavement walked for tiles and nails, then sign out.
PPE
- Safety helmet
- Safety boots with midsole protection
- Gloves for tiles and timber
- Eye protection when cutting
- Harness only if the method on the day says fall arrest, with a rescue plan
Tickets to confirm
- Working at height training for anyone going onto the roof
- CSCS or an equivalent card where the site requires it
- Asbestos awareness and a stop-and-report rule
- Hoist operator briefed on this site before the first lift
Emergency
- Stop work and make the area safe if that can be done without putting anyone else at risk.
- For a serious injury, a fire, or an immediate threat, ring 999 and send someone to the front of 12 Sample Street to meet the emergency services.
- Use the first-aid kit in the van. Do not move a person who may have fallen unless they are in immediate further danger.
- Tell the supervisor and the client contact. Keep the scene if it is safe to do so. Whether a report is due stays with the responsible person.
- If someone is caught on a roof after a fall-arrest event, start the rescue plan. Do not leave them suspended while the rest of the gang keeps tiling.
Nearest A&E: Exampletown General Hospital, 1 Sample Road, Exampletown EX2 3CD (fictional)
Legislation and guidance
Only the UK sources kept for this trade. This is not legal advice.
- Health and Safety at Work etc. Act 1974. Employers and the self-employed must protect workers and others so far as is reasonably practicable.
- Management of Health and Safety at Work Regulations 1999. The assessment must be suitable and sufficient, and the controls must be put in place.
- Personal Protective Equipment at Work Regulations 1992 (as amended 2022). PPE is the last resort in the hierarchy of control. It must be suitable, maintained, and provided to limb (b) workers as well as employees after the 2022 amendment.
- Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013. The responsible person reports specified injuries, diseases and dangerous occurrences. This RAMS does not decide whether a report is due.
- Construction (Design and Management) Regulations 2015. Where this is construction work, the contractor plans, manages and monitors it. This RAMS does not replace a construction phase plan.
- HSE L153 Managing health and safety in construction. HSE guidance on CDM 2015. Use it to judge whether the plan is proportionate to the job.
- Work at Height Regulations 2005. Avoid work at height where you can. Otherwise prevent a fall, and only then minimise the distance and the consequences.
- HSE INDG401 Working at height: a brief guide. Short HSE guide to the Work at Height Regulations. It does not replace a site-specific method.
- HSE HSG33 Health and safety in roof work. HSE guidance on fragile roofs, edge protection and short-duration roof work. Follow the current edition.
- Provision and Use of Work Equipment Regulations 1998. Work equipment must be suitable, maintained, and used by people who have been given the right information and training.
- Lifting Operations and Lifting Equipment Regulations 1998. Lifting equipment and lifting operations must be planned, supervised and carried out safely.
- Manual Handling Operations Regulations 1992. Avoid hazardous manual handling where reasonably practicable, assess what remains, and reduce the risk.
- Control of Substances Hazardous to Health Regulations 2002. Assess exposure to hazardous substances, including dusts, and control it. The safety data sheet informs the assessment.
- Control of Asbestos Regulations 2012. Do not disturb suspected asbestos. Stop and follow the survey and a specific plan. This RAMS is not an asbestos method.
- Control of Noise at Work Regulations 2005. Assess noise from tools such as cutters and breakers, and control exposure. Hearing protection is not the first control.
Sign-off
Left blank on purpose. A sample is not a signed RAMS. On a real job the competent person reviews it, and the people doing the work sign after the briefing.
Reviewed by (name)
Role
Signature
Date
| Name | Signature | Date | Card or licence |
|---|---|---|---|