Scaffolding RAMS template

Scaffold RAMS are often rejected because they read like a generic fall-from-height sheet and never mention ties, ground, or the pavement. The people who will stand under the scaffold, including the public, need a method that says how the structure is built, altered and handed over.

This sample separates erection, use and dismantle, and it points at CISRS competence and a TG20-compliant design or a bespoke design where the build is outside a standard configuration. It is a draft for the scaffold contractor's competent person, not a design certificate.

When to use it. Independent tied scaffolds, pavement gantries, temporary roofs, and mobile towers used as the working platform. Alterations by other trades are a stated prohibition, not an assumption.

Build a scaffolding RAMSSee a completed example

What this RAMS has to cover

Sample excerpt

From the scaffolding base inside RamsBox. It is not a RAMS for a real address until you add the site.

Collapse from poor ties, overload or weak ground. Who might be harmed: Operatives, other people on site, and anyone nearby

  1. Confirm design or TG20 configuration, pavement permission, and service locations.
  2. Brief the gang. Agree the exclusion zone and the public side.
  3. Set out sole boards and standards. Check the ground.

Hazards and controls

Collapse from poor ties, overload or weak ground

Who might be harmed: Operatives, other people on site, and anyone nearby

Initial 10 (High) · residual 5 (Medium)

  • Build to the stated TG20 configuration or the bespoke design. Do not improvise ties or bay lengths.
  • Check ground bearing. Use sole boards. Do not set standards on manhole covers, soft verge or frozen ground that will thaw.
  • Post the loading limit. Do not use the scaffold as a materials yard.

Falls while erecting or dismantling

Who might be harmed: Operatives doing the task

Initial 15 (High) · residual 5 (Medium)

  • Use a collective method: advanced guardrail or a sequential build that keeps a protected platform, as the system requires.
  • Harnesses only where the method says they are the control, with anchors and a rescue plan that works at that height.

Falling tubes, boards and fittings

Who might be harmed: Members of the public next to the work; Other contractors and visitors on site

Initial 12 (High) · residual 4 (Low)

  • Exclusion zone or a pavement gantry with brickguards and fans where people pass underneath.
  • Pass materials up. Do not throw fittings. Keep a gin wheel or rope only as the method describes.

Scaffold left incomplete and then used

Who might be harmed: Operatives doing the task; Other contractors and visitors on site

Initial 15 (High) · residual 5 (Medium)

  • Incomplete scaffolds are signed 'scaffold incomplete' and access is physically stopped.
  • Handover is recorded before other trades are allowed on.

Unauthorised alteration

Who might be harmed: Operatives, other people on site, and anyone nearby

Initial 15 (High) · residual 5 (Medium)

  • Tell every user at induction that ties, boards and guardrails are not to be moved.
  • If a tie must move for the works, the scaffold contractor does it and inspects afterwards.

Wind, impact from vehicles, or undermining by excavation

Who might be harmed: Operatives, other people on site, and anyone nearby

Initial 10 (High) · residual 4 (Low)

  • Stop erection in winds that make handling tubes unsafe.
  • Protect standards near vehicle routes. Recheck if an excavation opens beside the scaffold.

Relevant legislation and guidance

Only the UK sources kept for this trade. This is not legal advice, and RamsBox is not affiliated with HSE.

Sequence, tickets and PPE

  1. Confirm design or TG20 configuration, pavement permission, and service locations. TG20 or the design, the pavement permission, and the service drawings are on site before the first tube goes up.
  2. Brief the gang. Agree the exclusion zone and the public side. Agree the exclusion zone and which side the public uses. No one starts until that is set.
  3. Set out sole boards and standards. Check the ground. Sole boards on checked ground. Do not build off soft, sloping or unassessed ground.
  4. Erect lift by lift using the collective fall method for this system. Collective fall protection as this system requires. Do not climb an incomplete lift.
  5. Install ties as the design specifies, as the scaffold rises, not at the end. Ties go in as the scaffold rises, to the design, not left until the end.
  6. Fit guardrails, toe boards and brickguards. Stop access if a lift is incomplete. Guardrails, toe boards and brickguards on before the lift is used. Stop access if a lift is incomplete.
  7. Inspect, tag, and hand over in writing before other trades use it. Inspect, tag, and hand over in writing before any other trade uses the scaffold.
  8. Dismantle top down, with the exclusion zone back in place. Do not bomb tubes. Top down only. Exclusion zone back in place. Do not bomb tubes or boards.

DRAFT - needs competent person review. A competent person still has to check the draft against the site.

Questions on scaffolding RAMS

Does this replace a TG20 compliance sheet or a design drawing?

No. The RAMS should say which one applies. A standard configuration can follow TG20. Anything else needs a design. This draft tells you to attach that reference before the job starts.

How often is a scaffold inspected?

The base method includes inspection before first use, after alteration, after events that could affect stability, and at least every seven days, with a visible tag. That follows the Work at Height Regulations schedule.

Can a labourer move a tie to get a window in?

No. The draft says only the scaffold contractor alters ties, boards or guardrails, then re-inspects. Other trades stop and call them.

Is a RAMS a legal requirement for scaffolding?

Scaffolding is construction work. CDM 2015 expects it to be planned, and the Work at Height Regulations 2005 expect falls to be prevented during erection as well as use. TG20 and the NASC guidance are the usual technical references. The RAMS is the job-specific plan, not a copy of the TG20 eGuide.

Who should write a scaffolding RAMS?

The scaffolder or supervisor who will run the erection. A designer’s TG20 compliance sheet does not describe this pavement, these ties or this loading. The competent person signing the RAMS should be able to reject a tie pattern that does not match the building.

What is the difference between a risk assessment and a method statement for a scaffold?

The assessment covers falls, collapse, falling materials and the public. The method is the sequence: inspect the ground, set the exclusion, erect in the designed order, tie as you go, inspect, then hand over. Alterations by other trades belong in both.

Is a scaffold inspection the same document as the RAMS?

No. The inspection record shows the scaffold was checked. The RAMS shows how it will be put up and used on this job. You need both.

AI-assisted draft. A competent person must review it and approve it for the site before use. RamsBox does not provide health and safety advice and is not affiliated with HSE.